- Ogunsemore, O. S.; Alade, K. T.; Sunday, O. G. & Ekundayo, K. J.
- DOI: 10.5281/zenodo.24358281
- GAS Journal of Engineering and Technology (GASJET)
Repeated
cost overruns, delays and quality concerns in public buildings highlight the
importance of effective project planning in South-West Nigeria. This study
examined the association between project planning processes and public building
project delivery. Using a cross-sectional survey of building professionals
across six states, 402 questionnaires were administered from a population of
480, 305 were returned (75.9%), and 300 were included in the analysis (74.6% of
those distributed). Descriptive statistics, multiple regression and seemingly
unrelated regression (SUR) were employed. The mean overall planning score was
4.200 (SD = 0.720); procurement planning had the highest mean (M = 4.324),
while risk management had the lowest (M = 3.957). The overall-delivery
regression was significant, F(8, 291) = 32.564, p < .001, R² = .473, with
significant positive coefficients for resource planning (b = 0.206, p = .001),
scheduling (b = 0.132, p = .006) and procurement planning (b = 0.195, p =
.001). The SUR Wald χ² statistics were 214.68 for cost, 286.41 for time and
267.53 for quality (all p < .001). Planning practices were jointly
associated with perceived delivery across all three outcomes, although the
pattern of individual associations differed by model. Integrated planning, with
particular emphasis on resource availability, realistic scheduling and
procurement readiness, is recommended to strengthen public building project
delivery.
Keywords: project planning; scheduling; resource planning; procurement; cost and time performance; public buildings; South-West Nigeria.